Energy experts generally agree that the electrical grid in the United States needs to be upgraded if the country is to increase its use of renewable-energy sources like wind power and significantly reduce emissions of greenhouse gases. But plans to string new high-voltage lines to bring wind power from the midsection of the country to the coasts, where most of the demand is, could be expensive and unnecessary, and a distraction from more urgent needs, some experts say.

A new national grid, which has been likened to the Interstate Highway System constructed in the 1950s, has been proposed by groups such as the Center for American Progress, a Washington-based think tank, and AEP, a large utility; elements of the plans have been included in recent federal legislation. According to this vision, new high-voltage transmission lines costing billions of dollars would be built across the country, augmenting the existing patchwork of transmission lines much as the Interstate Highway System laid down high-speed roadways over an existing network of highways. But such a plan is “only a dream,” says Paul Joskow, president of the Sloan Foundation and a professor of economics at MIT. “It’s expensive. It’s politically contentious. In the end, I think you’re better off spending the money on other things.”

What’s needed instead are improved local and regional electricity transmission, the development of an efficient and adaptable smart grid, and the demonstration of technology such as carbon capture and sequestration, which could prove a cheaper way to reduce carbon dioxide emissions than transmitting power from North Dakota to New York City.

To be sure, new local and regional transmission lines are needed to bring wind power to market, since many wind farms are located in remote areas without the necessary connections to the grid. Indeed, last week, investor T. Boone Pickens said that he’s halting his planned four-gigawatt wind farm in Texas in part because of a lack of transmission lines to carry the power from the farm to urban centers. And Steven Specker, the president and CEO of the Electric Power Research Institute, says that the lack of such transmission is the biggest obstacle to the growth of renewables.

But national transmission lines are a different story: they would face large obstacles and may not be necessary. Unlike local and regional transmission projects, where regulatory mechanisms are in place to distribute the costs of construction, it’s not clear who would pay for a national grid. There could also be resistance from states between the wind farms and the coasts, which would have to give up land for the transmission lines without benefitting from the power that they carry. What’s more, some politicians have moved to block such lines because wind power from North Dakota could threaten local wind power companies in places such as New England.

20 comments. Share your thoughts »

Credit: NASA/Goddard Space Flight Center Scientific Visualization Studio

Tagged: Business, Energy, renewable energy, electricity, greenhouse gases, wind power, smart grid, electric grid, power grid, transmission lines

Reprints and Permissions | Send feedback to the editor

From the Archives

Close

Introducing MIT Technology Review Insider.

Already a Magazine subscriber?

You're automatically an Insider. It's easy to activate or upgrade your account.

Activate Your Account

Become an Insider

It's the new way to subscribe. Get even more of the tech news, research, and discoveries you crave.

Sign Up

Learn More

Find out why MIT Technology Review Insider is for you and explore your options.

Show Me