Some Assembly Required
Inside the assembly building, Ares I-X will come to life. By the time they finish, engineers will have spent several weeks stacking the rocket's components, delicately maneuvering one piece on top of another with massive cranes. The completed Ares I-X will be nearly identical to Ares I from the outside: a sleek, two-stage rocket with the crew module on top, as far away from the propulsion system as possible. To make the test-flight data as accurate as possible, it will also be similar in mass and size, standing approximately 99 meters tall, varying from 3.7 to 5.5 meters in diameter, and weighing about 816,000 kilograms when fully fueled.

Three more unmanned test flights are planned after the August launch. Ares I-Y will be identical to the final rocket--nothin­g simulated--and is tentatively scheduled for launch in 2013. The Orion 1 and 2 launches, designed to test the crew module, are planned for the following year, and the first manned launch of Ares I is set for 2015.

NASA is staking its future on long-term exploration, moving beyond low Earth orbit and using the Ares rockets to get there. "The space shuttle has been a great machine, but we need a vehicle [with] better safety and reliability, and with more capabilities," says Cook. Ares I will have greater range than the shuttle and will cost less to maintain and launch, he says, so it will be possible to venture farther into space, and more often. When Ares V is completed, NASA hopes to build an outpost on the moon, sustaining a human presence there by 2020. The base will allow them to research and test new technologies useful for manned exploration of Mars. Says Cook, "This is what we came to NASA to do."

Video

Print

Related Articles

Space Companies Hatch Plans for Reusable Rockets

Such a rocket would dramatically reduce the costs of spaceflight—a promise NASA's space shuttle failed to deliver on.

NASA Road-Tests New Moon Rover

Engineers put the electric rover through its paces in the Arizona desert.

NASA's Plans Lack the Cash

Can the commercial sector rescue the U.S. human spaceflight program?

Close Comments

To comment, please sign in or register

Forgot my password

Gaetano Marano

246 Comments

  • 957 Days Ago
  • 06/29/2009

latest news say that the Ares 1-X is too dangerous to fly >>>

.

latest news (published in an Orlando Sentinel's article) say that the USAF believes the Ares 1-X too dangerous to fly:

http://www.orlandosentinel.com/news/local/orl-nasa-rocket-troubles-062809,0,4229034.story

as I've already said 1.5 years ago in this article:

http://www.ghostnasa.com/posts/021chillinglaunch.html

however, other options are possible for the ESAS plan, like those I'm suggesting these days to the Human Space Flight Plans Committee:

http://ow.ly/f3vQ

.

Reply

IggyDalrymple

22 Comments

  • 954 Days Ago
  • 07/02/2009

Building NASA's Future

James Hansen has pissed away NASA's credibility.  He symbolizes how so many modern scientists massage data to reflect their biases.

Reply

Gaetano Marano

246 Comments

  • 952 Days Ago
  • 07/04/2009

>>> don't adopt the SERIOUSLY FLAWED  Direct concept >>>

.

just posted my suggestion #10 for the Human Space Flight Plans Committee and NASA:

"absolutely don't adopt the SERIOUSLY FLAWED Direct concept"

http://ow.ly/f3vQ

.

Reply

Advertisement

MAGAZINE

Can We Build Tomorrow's Breakthroughs?

Manufacturing in the United States is in trouble. That's bad news not just for the country's economy but for the future of innovation.

Sponsored Content

Technologies from National Instruments

Adding Data Logging
Log measured data to a file and open it in Microsoft Excel

> Click here for more National Instruments Videos <
Whitepaper

Temperature Measurements with Thermocouples: How-To Guide

This document is part of the “How-To Guide for Most Common Measurements” centralized resource portal. This tutorial provides a detailed guide for measurement and device considerations to take temperature measurements using thermocouples. Get an introduction to thermocouples, which are inexpensive sensing devices widely used with PC-based data acquisition systems. Also review some specific thermocouple examples and learn how thermocouples work and ways to integrate them into a data acquisition measurement system.

View full PDF > Listen to story >
Find us on Youtube

Videos

A Robot Recruit that Can Do It All

More

Advertisement

Technology Review Lists

TR50

Our list of the 50 most innovative companies, including the following:

Akamai

Lattice Power

Twitter

Crowdcast

More

Advertisement

Facebook

Advertisement